How do you delete a WBS element in SAP?

How do you delete a WBS element in SAP?

You can now cancel the deletion flag for the required WBS elements….Activities.

Function Menu Path
Delete WBS elements directly Edit Delete Delete object or
Provide the WBS element with a deletion flag. Edit Status Deletion flag

How do you release a WBS budget in SAP?

Activities

  1. Choose Logistics or Accounting Project System Controlling Budgeting Release. Change. The Change Release: Initial Screen appears.
  2. Enter the necessary data and choose Release. The Change Release: WBS Element Overview screen appears.

How do I update a WBS budget in SAP?

Budget upload process in SAP PS

  1. To upload the budget.
  2. Enter the project definition RR/1001 and enter.
  3. Then enter the budget manually against the different WBS elements you want in the budget column.
  4. Then press enter.
  5. Next Screen will come and we need to put the receiver year.
  6. Then go to supplement and then click on post.

How do I delete a project in SAP?

Go to to transaction CJ02, enter Project Definition and press SHIFT + F1 or click on “Project Definition” button. Then go to Menu Bar > Edit > Object > Delete, or press SHIFT + F2. Click “Yes” on the displayed dialog to confirm deletion.

Is it possible to delete a WBS element?

I would like to delete a WBS Element. When I try to do it, I get the error message ” WBS element ALI-0002-0001-03-01 has an account assignment and cannot be deleted”. You cannot delete WBS element ALI-0002-0001-03-01. It has dependent objects assigned to it, such as networks, network activities, orders, purchaser requisitions, or purchase orders.

What does sap stand for in WBS element?

CJ02 – Change Work Breakdown Structure CJ03 – Display Work Breakdown Structure CJ88 – Settle Projects and Networks CJ8G – Actual Settlement: Projects/Networks CJI3 – Project Actual Cost Line Items CJI5 – Project Commitment Line Items OPSA – Maintain Project Profile CJ30 – Change Project Original budget CJ40 – Change Project Plan

What are the elements of the WBS budget?

CJ03 – Display Work Breakdown Structure CJ88 – Settle Projects and Networks CJ8G – Actual Settlement: Projects/Networks CJI3 – Project Actual Cost Line Items CJI5 – Project Commitment Line Items OPSA – Maintain Project Profile CJ30 – Change Project Original budget CJ40 – Change Project Plan

Can you delete integrated planning elements in SAP?

Integrated planning WBS elements can be deleted as long as no planned costs or revenues have been posted. You cannot delete WBS elements with the status Released, if they are distributed via ALE or if active simulation versions exist.